PA File No.: PA/00993/23
ERA Reference: EA/00019/22
Project Title: Construction of an Organic Processing Plant in Malta
Location: ECOHIVE Complex, Naxxar.
Project Description Statement:
EIA Screening Report:
EIA Required: Yes
Status: Concluded
EIA Terms of Reference Consultation Period:
11/08/2022 - 17/09/2022
Comments received during consultation:
Terms Of Reference:
EIA Report:
Consultation Dates on EIA Report:
16/04/2023 - 17/05/2023
Board Decision in Public Date:
15/12/2023
Board Decision in Public Time:
10:00
Board Decision in Public Location:
ERA offices and online (hybrid)
MEMO to ERA Board:
Date Uploaded:
05/12/2023
ERA’s Assessment & Recommendation:
Date Uploaded:
15/12/2023
Responsible authorities and nature of decisions:
- the authority responsible for the Environmental Impact Assessment process: ERA
- the nature of the decisions to be taken: development consent decision
- the authorities responsible for the development consent decisions: Planning Authority