ERA Reference: EA/00034/24
Project Title: Demolition of existing boundary walls, site clearance, and excavation to the required levels, followed by the construction of an extension to the existing Sewage Treatment Plant. The extension will include a pre-treatment area, a new water plant room, thickening and dewatering facilities, a ferric dosing kiosk, a subterranean sludge holding reservoir, and an MBR area. The proposal also includes the deviation of an existing public rural road and the construction of traditional rubble walls along the site perimeter.
Location: Site at Ic-Cumnija, Il-Mejjieli, Mellieha
Project Description Statement:
EIA Screening Report:
Date Uploaded:
11/11/2024
EIA Required: No
Status: Awaiting further studies
Responsible authorities and nature of decisions:
- the authority responsible for the Environmental Impact Assessment process: ERA
- the nature of the decisions to be taken: development consent decision
- the authorities responsible for the development consent decisions: Planning Authority