PA File No.: PA/02053/20 & PA/06425/20
ERA Reference: EA/00006/21
Project Title: Proposed Network Upgrading of Msida Creek including flyover at Misrah 5 t’Ottubru and misrah il-Menqa, road widening at Triq Marina, roundabout junction at Triq il-Wied tal-Imsida and two pedestrian bridges at Triq Marina and Misrah Guze Ellul Mercer; and Junction upgrading at p/w Triq Wied tal-Imsida.
Location: Msida Creek, ix-Xatt ta' Xbiex,Triq Guze' Ellul Mercer, Triq Marina, Xatt lImsida, Misrah il-Hamsa ta' Ottubru, Misrah tal-Menqa,Triq il-Wied talImsida,Triq M. A. Vassalli, Triq D' Argens, Msida; and Site at, p/o, Triq il-Wied tal-Imsida, Msida.
Project Description Statement:
EIA Screening Report:
Date Uploaded:
26/02/2021
EIA Required: No
Status: Concluded
PA/02053/20 - Revised PDS: Schedule II - PDS (February 2023)
PA/02053/20 - Revised PDS: Schedule II - PDS - Appendix (February 2023)
PA/02053/20 - Revised EIA Screening Report: EIA Screening Report (March 2023)
Date Uploaded: 21/03/2023
PA/02053/20 - ERA Correspondence: ERA Correspondence incl. conditions (July 2023)
Responsible authorities and nature of decisions:
- the authority responsible for the Environmental Impact Assessment process: ERA
- the nature of the decisions to be taken: development consent decision
- the authorities responsible for the development consent decisions: Planning Authority