PA File No.: PA/04712/20
ERA Reference: EA/00017/21
Project Title: Proposed installation of photovoltaic farm infrastructure over restored quarry including ancillary services.
Location: Tal-Hagra, Triq Tas-Sejba c/w, Triq il-Madonna tal-Gilju, Mqabba
Project Description Statement:
EIA Screening Report:
Date Uploaded:
17/09/2021
EIA Required: No
Status: Concluded
ERA Correspondence following additional information: ERA Correspondence (incl. conditions) (March 2023)
Date Uploaded: 21/03/2023
Responsible authorities and nature of decisions:
- the authority responsible for the Environmental Impact Assessment process: ERA
- the nature of the decisions to be taken: development consent decision
- the authorities responsible for the development consent decisions: Planning Authority