PA File No.: PA/03162/19
ERA Reference: EA/00036/19
Project Title: Structural alterations including construction of internal walls to change existing slaughter house into a meat processing plant, agricultural store approved by PA/5554/02 into a cold store & loading/unloading bay. Sanctioning of the construction of a settling tank and cesspit. Construction of a Class 7 poultry slaughtering and processing house including underlying basement garage.
Location: Site at, Ta Gauci Poultry, New Street in, Triq Burmarrad, Burmarrad, San Pawl il-Bahar.
Project Description Statement:
EIA Screening Report:
Status: Concluded
ERA’s assessment & recommendation:
Responsible authorities and nature of decisions:
- the authority responsible for the Environmental Impact Assessment process: ERA
- the nature of the decisions to be taken: development consent decision
- the authorities responsible for the development consent decisions: Planning Authority